Dept. of Trans. PROGRESS Serial No. Contract No. 21-298-08-34 05-1E0104 PROGRESS PAYMENT VOUCHER %complete: %time: 52% 42% Location: Federal Project: 05-SB-101-46.6/47.1 CSTG-Q101(362) Progress payment No. 007 Payment period ending: 10-20-21 SPECIALTY CONSTRUCTION INC 645 CLARION CT SAN LUIS OBISPO CA 93401 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 2,415,487.96 894,908.04 2. a. Extra Work 26,753.50 16,159.02 b. Adustment Comp. -2,500.00 0.00 3. Materials on Hand 4. Earned Subject to Retention 2,439,741.46 911,067.06 5. Mobilization 6. Total Work Completed 2,439,741.46 7. Deductions -7,000.00 8,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 2,432,741.46 919,067.06 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 919,067.06