Dept. of Trans. PROGRESS Serial No. Contract No. 19-141-15-27 05-1F0804 PROGRESS PAYMENT VOUCHER %complete: %time: 13% 5% Location: Federal Project: 05-MON-1-2.5/67.3 B1ST-P001(643) Progress payment No. 003 Payment period ending: 05-20-19 SERAFIX ENGINEERING CONTRACTORS INC 7 CROW CANYON CT #250 SAN RAMON CA 94583 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 184,220.00 172,220.00 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 389,724.00 293,037.00 4. Earned Subject to Retention 573,944.00 465,257.00 5. Mobilization 225,000.00 225,000.00 6. Total Work Completed 409,220.00 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 798,944.00 690,257.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 690,257.00