Dept. of Trans. PROGRESS Serial No. Contract No. 17-298-08-37 05-1F3404 PROGRESS PAYMENT VOUCHER %complete: %time: 99% 85% Location: Federal Project: 05-SCR-236-0.1/17.7 STP-P236(1) Progress payment No. 007 Payment period ending: 10-20-17 GRANITE ROCK COMPANY 120 GRANITE ROCK WAY SAN JOSE CA 95136 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 3,227,632.69 -62,469.60 2. a. Extra Work 51,857.66 30,992.78 b. Adustment Comp. 99,564.62 0.00 3. Materials on Hand 4. Earned Subject to Retention 3,379,054.97 -31,476.82 5. Mobilization 340,000.00 0.00 6. Total Work Completed 3,719,054.97 7. Deductions -7,000.00 60,469.52 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 3,712,054.97 28,992.70 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 28,992.70