Dept. of Trans. PROGRESS Serial No. Contract No. 18-295-20-26 05-1F3504 PROGRESS PAYMENT VOUCHER %complete: %time: 35% 92% Location: Federal Project: 05-SCR-129-3.0/3.5 HSST-S129(18) Progress payment No. 002 Payment period ending: 10-20-18 GRANITE ROCK COMPANY 5225 HELLYER AVENUE #220 SAN JOSE CA 95138 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 687,852.19 667,752.19 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 687,852.19 667,752.19 5. Mobilization 122,360.00 122,360.00 6. Total Work Completed 810,212.19 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 810,212.19 790,112.19 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 790,112.19