Dept. of Trans. PROGRESS Serial No. Contract No. 19-109-11-09 05-1F3504 PROGRESS PAYMENT VOUCHER %complete: %time: 91% 76% Location: Federal Project: 05-SCR-129-3.0/3.5 HSST-S129(18) Progress payment No. 008 Payment period ending: 04-20-19 GRANITE ROCK COMPANY 5225 HELLYER AVENUE #220 SAN JOSE CA 95138 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 2,046,119.25 4,372.75 2. a. Extra Work 41,327.22 0.00 b. Adustment Comp. -32,000.00 0.00 3. Materials on Hand 4. Earned Subject to Retention 2,055,446.47 4,372.75 5. Mobilization 128,800.00 0.00 6. Total Work Completed 2,184,246.47 7. Deductions -17,136.98 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 2,167,109.49 4,372.75 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 4,372.75