Dept. of Trans. PROGRESS Serial No. Contract No. 16-116-14-24 05-1F3604 PROGRESS PAYMENT VOUCHER %complete: %time: 73% 75% Location: Federal Project: 05-SCR-1-31.6/36.3 NONE Progress payment No. 005 Payment period ending: 04-20-16 BUGLER CONSTRUCTION 4847 HOPYARD RD #4 #395 PLEASANTON CA 94588 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 468,486.00 68,717.00 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 468,486.00 68,717.00 5. Mobilization 65,000.00 0.00 6. Total Work Completed 533,486.00 7. Deductions -27,179.25 422.55 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 506,306.75 69,139.55 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 69,139.55