Dept. of Trans. PROGRESS Serial No. Contract No. 15-260-14-37 05-1F3904 PROGRESS PAYMENT VOUCHER %complete: %time: 86% 71% Location: Federal Project: 05-SB-101-1.6/22.5 NONE 05-SB-154-30.2 Progress payment No. 002 Payment period ending: 09-20-15 PETERSON-CHASE GENERAL ENGINEERING CONSTRUCTION, INC. 1792 KAISER AVENUE IRVINE CA 92614 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 243,624.44 19,361.40 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 243,624.44 19,361.40 5. Mobilization 60,000.00 0.00 6. Total Work Completed 303,624.44 7. Deductions -26,987.12 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 276,637.32 19,361.40 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 19,361.40