Dept. of Trans. AFTER ACCEPTANCE Serial No. Contract No. 20-150-10-12 05-1F4304 PROGRESS PAYMENT VOUCHER %complete: %time: 100% 100% Location: Federal Project: 05-SBT-25-R49.7/R52.4 HSNH-P025(32) Progress payment No. 013 Payment period ending: 05-04-20 GRANITE ROCK COMPANY 5225 HELLYER AVENUE #220 SAN JOSE CA 95138 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 5,159,645.09 32,399.00 2. a. Extra Work 82,655.95 9,391.13 b. Adustment Comp. -125,473.98 -95,850.13 3. Materials on Hand 4. Earned Subject to Retention 5,116,827.06 -54,060.00 5. Mobilization 590,000.00 0.00 6. Total Work Completed 5,706,827.06 7. Deductions -26,000.00 84,193.36 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 5,680,827.06 30,133.36 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 30,133.36