Dept. of Trans. SEMI-FINAL Serial No. Contract No. 20-169-13-13 05-1F4304 PROGRESS PAYMENT VOUCHER %complete: %time: 100% 100% Location: Federal Project: 05-SBT-25-R49.7/R52.4 HSNH-P025(32) Progress payment No. 014 Payment period ending: 05-04-20 GRANITE ROCK COMPANY 5225 HELLYER AVENUE #220 SAN JOSE CA 95138 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 5,161,675.33 2,030.24 2. a. Extra Work 82,655.95 0.00 b. Adustment Comp. -125,473.98 0.00 3. Materials on Hand 4. Earned Subject to Retention 5,118,857.30 2,030.24 5. Mobilization 590,000.00 0.00 6. Total Work Completed 5,708,857.30 7. Deductions -26,000.00 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 5,682,857.30 2,030.24 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 2,030.24