Dept. of Trans. PROGRESS Serial No. Contract No. 22-081-21-14 05-1F5004 PROGRESS PAYMENT VOUCHER %complete: %time: 40% 56% Location: Federal Project: 05-SB-101-70.6/71.2 ACST-X083(19) 05-SB-135-0.1 Progress payment No. 014 Payment period ending: 03-20-22 CALPORTLAND CONSTRUCTION 1625 EAST DONOVAN RD SANTA MARIA CA 93454 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 3,939,913.07 607,308.56 2. a. Extra Work 35,821.59 500.00 b. Adustment Comp. 110,020.72 13,343.76 3. Materials on Hand 375,520.00 0.00 4. Earned Subject to Retention 4,461,275.38 621,152.32 5. Mobilization 332,500.00 0.00 6. Total Work Completed 4,418,255.38 7. Deductions 0.00 5,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 4,793,775.38 626,152.32 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 626,152.32