Dept. of Trans. SEMI-FINAL Serial No. Contract No. 24-201-14-38 05-1F6204 PROGRESS PAYMENT VOUCHER %complete: %time: 100% 100% Location: Federal Project: 05-SCR-152-1.9/R2.0 NONE Progress payment No. 011 Payment period ending: 12-27-23 BRIDGEWAY CIVIL CONSTRUCTORS INC 3333 VACA VALLEY PKWY #2000 VACAVILLE CA 95688 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 1,155,683.00 12,872.60 2. a. Extra Work 52,851.31 4,039.15 b. Adustment Comp. -4,673.42 0.00 3. Materials on Hand 4. Earned Subject to Retention 1,203,860.89 16,911.75 5. Mobilization 120,000.00 0.00 6. Total Work Completed 1,323,860.89 7. Deductions -10,897.15 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 1,312,963.74 16,911.75 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 16,911.75