Dept. of Trans. PROGRESS Serial No. Contract No. 21-116-10-29 05-1F6804 PROGRESS PAYMENT VOUCHER %complete: %time: 95% 73% Location: Federal Project: 05-MON-1-39.8/74.6 ACST-P001(662) Progress payment No. 015 Payment period ending: 04-20-21 GRANITE ROCK COMPANY 5225 HELLYER AVENUE #220 SAN JOSE CA 95138 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 20,504,407.53 459,557.94 2. a. Extra Work 1,010,784.83 236,302.68 b. Adustment Comp. -114,149.73 0.00 3. Materials on Hand 4. Earned Subject to Retention 21,401,042.63 695,860.62 5. Mobilization 1,545,894.00 0.00 6. Total Work Completed 22,946,936.63 7. Deductions -10,000.00 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 22,936,936.63 695,860.62 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 695,860.62