Dept. of Trans. PROGRESS Serial No. Contract No. 21-144-19-46 05-1F6804 PROGRESS PAYMENT VOUCHER %complete: %time: 95% 80% Location: Federal Project: 05-MON-1-39.8/74.6 ACST-P001(662) Progress payment No. 016 Payment period ending: 05-20-21 GRANITE ROCK COMPANY 5225 HELLYER AVENUE #220 SAN JOSE CA 95138 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 20,642,439.08 138,031.55 2. a. Extra Work 1,073,298.95 62,514.12 b. Adustment Comp. -114,149.73 0.00 3. Materials on Hand 4. Earned Subject to Retention 21,601,588.30 200,545.67 5. Mobilization 1,545,894.00 0.00 6. Total Work Completed 23,147,482.30 7. Deductions -20,000.00 -10,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 23,127,482.30 190,545.67 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 190,545.67