Dept. of Trans. PROGRESS Serial No. Contract No. 21-173-15-12 05-1F6804 PROGRESS PAYMENT VOUCHER %complete: %time: 96% 86% Location: Federal Project: 05-MON-1-39.8/74.6 ACST-P001(662) Progress payment No. 017 Payment period ending: 06-20-21 GRANITE ROCK COMPANY 5225 HELLYER AVENUE #220 SAN JOSE CA 95138 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 20,775,616.14 133,177.07 2. a. Extra Work 1,156,618.95 83,320.00 b. Adustment Comp. -114,149.73 0.00 3. Materials on Hand 4. Earned Subject to Retention 21,818,085.36 216,497.07 5. Mobilization 1,545,894.00 0.00 6. Total Work Completed 23,363,979.36 7. Deductions -20,000.00 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 23,343,979.36 216,497.07 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 216,497.07