Dept. of Trans. PROGRESS Serial No. Contract No. 21-207-15-38 05-1F6804 PROGRESS PAYMENT VOUCHER %complete: %time: 98% 92% Location: Federal Project: 05-MON-1-39.8/74.6 ACST-P001(662) Progress payment No. 018 Payment period ending: 07-20-21 GRANITE ROCK COMPANY 5225 HELLYER AVENUE #220 SAN JOSE CA 95138 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 20,785,672.86 10,056.72 2. a. Extra Work 1,610,708.73 454,089.78 b. Adustment Comp. -114,149.73 0.00 3. Materials on Hand 4. Earned Subject to Retention 22,282,231.86 464,146.50 5. Mobilization 1,545,894.00 0.00 6. Total Work Completed 23,828,125.86 7. Deductions -20,000.00 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 23,808,125.86 464,146.50 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 464,146.50