Dept. of Trans. SEMI-FINAL Serial No. Contract No. 22-342-16-14 05-1F6804 PROGRESS PAYMENT VOUCHER %complete: %time: 100% 100% Location: Federal Project: 05-MON-1-39.8/74.6 ACST-P001(662) Progress payment No. 026 Payment period ending: 02-11-22 GRANITE ROCK COMPANY 5225 HELLYER AVENUE #220 SAN JOSE CA 95138 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 20,952,711.86 0.00 2. a. Extra Work 2,220,419.48 34,024.84 b. Adustment Comp. -630,718.45 0.00 3. Materials on Hand 4. Earned Subject to Retention 22,542,412.89 34,024.84 5. Mobilization 1,545,894.00 0.00 6. Total Work Completed 24,088,306.89 7. Deductions -5,323.50 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 24,082,983.39 34,024.84 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 34,024.84