Dept. of Trans. PROGRESS Serial No. Contract No. 19-353-15-00 05-1F7004 PROGRESS PAYMENT VOUCHER %complete: %time: 39% 37% Location: Federal Project: 05-MON-101-73.1/87.3 B1NH-Q101(350) Progress payment No. 005 Payment period ending: 12-20-19 GRANITE ROCK COMPANY 5225 HELLYER AVENUE #220 SAN JOSE CA 95138 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 9,266,343.93 1,401,872.56 2. a. Extra Work 30,238.18 0.00 b. Adustment Comp. -913.23 -913.23 3. Materials on Hand 777,478.55 -11,242.05 4. Earned Subject to Retention 10,073,147.43 1,389,717.28 5. Mobilization 1,045,000.00 0.00 6. Total Work Completed 10,340,668.88 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 11,118,147.43 1,389,717.28 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 1,389,717.28