Dept. of Trans. PROGRESS Serial No. Contract No. 20-175-11-13 05-1F7004 PROGRESS PAYMENT VOUCHER %complete: %time: 85% 68% Location: Federal Project: 05-MON-101-73.1/87.3 B1NH-Q101(350) Progress payment No. 011 Payment period ending: 06-20-20 GRANITE ROCK COMPANY 5225 HELLYER AVENUE #220 SAN JOSE CA 95138 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 21,773,511.98 4,269,371.05 2. a. Extra Work 42,180.52 11,942.34 b. Adustment Comp. -913.23 0.00 3. Materials on Hand 4. Earned Subject to Retention 21,814,779.27 4,281,313.39 5. Mobilization 1,100,000.00 0.00 6. Total Work Completed 22,914,779.27 7. Deductions -1,000.00 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 22,913,779.27 4,281,313.39 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 4,281,313.39