Dept. of Trans. FINAL Serial No. Contract No. 22-237-16-03 05-1F7004 PROGRESS PAYMENT VOUCHER %complete: %time: 100% 100% Location: Federal Project: 05-MON-101-73.1/87.3 B1NH-Q101(350) Progress payment No. 024 Payment period ending: 05-13-21 GRANITE ROCK COMPANY 5225 HELLYER AVENUE #220 SAN JOSE CA 95138 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 24,651,792.15 0.00 2. a. Extra Work 794,364.25 0.00 b. Adustment Comp. -891,278.90 0.00 3. Materials on Hand 4. Earned Subject to Retention 24,554,877.50 0.00 5. Mobilization 1,100,000.00 0.00 6. Total Work Completed 25,654,877.50 7. Deductions -1,000.00 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 25,653,877.50 0.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 0.00