Dept. of Trans. PROGRESS Serial No. Contract No. 19-022-09-09 05-1F7104 PROGRESS PAYMENT VOUCHER %complete: %time: 89% 83% Location: Federal Project: 05-SB-1-R0.0/19.3 ACNH-P001(632) Progress payment No. 009 Payment period ending: 01-20-19 CALPORTLAND CONSTRUCTION PO BOX 1280 SANTA MARIA CA 93456 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 12,057,055.97 388,723.42 2. a. Extra Work 478,645.69 57,227.25 b. Adustment Comp. -13,680.95 -2,021.05 3. Materials on Hand 111,885.53 -76,052.45 4. Earned Subject to Retention 12,633,906.24 367,877.17 5. Mobilization 1,500,000.00 0.00 6. Total Work Completed 14,022,020.71 7. Deductions -2,000.00 -2,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 14,131,906.24 365,877.17 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 365,877.17