Dept. of Trans. SEMI-FINAL Serial No. Contract No. 17-066-11-19 05-1F7304 PROGRESS PAYMENT VOUCHER %complete: %time: 100% 100% Location: Federal Project: 05-MON-156-R0.1/R1.6 HSNH-PG P156-019E Progress payment No. 005 Payment period ending: 11-17-16 CORAL CONSTRUCTION COMPANY PO BOX 347 WILSONVILLE OR 97070 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 699,625.50 -14,299.50 2. a. Extra Work 69,026.13 30,125.00 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 768,651.63 15,825.50 5. Mobilization 75,000.00 0.00 6. Total Work Completed 843,651.63 7. Deductions -10,000.00 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 833,651.63 15,825.50 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 15,825.50