Dept. of Trans. PROGRESS Serial No. Contract No. 21-264-17-58 05-1F75U4 PROGRESS PAYMENT VOUCHER %complete: %time: 65% 81% Location: Federal Project: 05-MON-101-R36.9/47.7 1NHG-Q101(338) Progress payment No. 031 Payment period ending: 09-20-21 OHL USA INC 1920 MAIN ST #310 IRVINE CA 92614 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 41,505,984.28 2,207,632.99 2. a. Extra Work 1,525,836.02 17,542.10 b. Adustment Comp. 834,258.29 -1,137.69 3. Materials on Hand 1,102,734.56 -82,953.17 4. Earned Subject to Retention 44,968,813.15 2,141,084.23 5. Mobilization 7,100,000.00 0.00 6. Total Work Completed 50,966,078.59 7. Deductions -52,070.51 -21,034.80 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 52,016,742.64 2,120,049.43 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 2,120,049.43