Dept. of Trans. PROGRESS Serial No. Contract No. 22-054-07-50 05-1F75U4 PROGRESS PAYMENT VOUCHER %complete: %time: 71% 91% Location: Federal Project: 05-MON-101-R36.9/47.7 1NHG-Q101(338) Progress payment No. 037 Payment period ending: 02-20-22 OHL USA INC 1920 MAIN ST #310 IRVINE CA 92614 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 47,864,323.71 1,087,785.96 2. a. Extra Work 2,031,421.24 0.00 b. Adustment Comp. 701,449.69 -260,946.94 3. Materials on Hand 158,089.91 0.00 4. Earned Subject to Retention 50,755,284.55 826,839.02 5. Mobilization 7,100,000.00 0.00 6. Total Work Completed 57,697,194.64 7. Deductions -62,070.51 10,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 57,793,214.04 836,839.02 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 836,839.02