Dept. of Trans. PROGRESS Serial No. Contract No. 21-265-10-11 05-1F7904 PROGRESS PAYMENT VOUCHER %complete: %time: 16% 24% Location: Federal Project: 05-SB-101-55.9/56.2 NONE Progress payment No. 010 Payment period ending: 09-20-21 SPECTRUM CONSTRUCTION GROUP INC 16 GOODYEAR #140 IRVINE CA 92618 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 600,398.93 -71,805.60 2. a. Extra Work 24,327.43 0.00 b. Adustment Comp. 3. Materials on Hand 170,320.00 170,320.00 4. Earned Subject to Retention 795,046.36 98,514.40 5. Mobilization 318,750.00 0.00 6. Total Work Completed 943,476.36 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 1,113,796.36 98,514.40 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 98,514.40