Dept. of Trans. PROGRESS Serial No. Contract No. 21-298-11-36 05-1F8204 PROGRESS PAYMENT VOUCHER %complete: %time: 90% 50% Location: Federal Project: 05-MON-101-R6.7/R6.7 ACNH-Q101(376) Progress payment No. 010 Payment period ending: 10-20-21 WHITAKER CONSTRUCTION GROUP INC 2752 CONCRETE CT PASO ROBLES CA 93446 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 3,544,757.68 2,943.60 2. a. Extra Work 49,955.11 13,398.16 b. Adustment Comp. 9,876.00 0.00 3. Materials on Hand 4. Earned Subject to Retention 3,604,588.79 16,341.76 5. Mobilization 129,250.00 0.00 6. Total Work Completed 3,733,838.79 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 3,733,838.79 16,341.76 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 16,341.76