Dept. of Trans. PROGRESS Serial No. Contract No. 16-328-11-09 05-1G1904 PROGRESS PAYMENT VOUCHER %complete: %time: 89% 59% Location: Federal Project: 05-SB-0-0.0 STP-000C(408) Progress payment No. 007 Payment period ending: 11-20-16 PETERSON-CHASE GEN ENGINEERING CONSTRUCTION INC 16351 CONSTRUCTION CIR WEST IRVINE CA 92606-4414 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 1,037,816.22 0.00 2. a. Extra Work 3,309.19 3,309.19 b. Adustment Comp. 3. Materials on Hand 45,180.93 -236.25 4. Earned Subject to Retention 1,086,306.34 3,072.94 5. Mobilization 55,000.00 0.00 6. Total Work Completed 1,096,125.41 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 1,141,306.34 3,072.94 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 3,072.94