Dept. of Trans. AFTER ACCEPTANCE Serial No. Contract No. 17-167-13-35 05-1G1904 PROGRESS PAYMENT VOUCHER %complete: %time: 100% 100% Location: Federal Project: 05-SB-0-0.0 STP-000C(408) Progress payment No. 009 Payment period ending: 06-07-17 PETERSON-CHASE GEN ENGINEERING CONSTRUCTION INC 16351 CONSTRUCTION CIR WEST IRVINE CA 92606-4414 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 1,139,555.08 0.00 2. a. Extra Work 26,115.30 6,841.83 b. Adustment Comp. 3. Materials on Hand 0.00 -45,180.93 4. Earned Subject to Retention 1,165,670.38 -38,339.10 5. Mobilization 55,000.00 0.00 6. Total Work Completed 1,220,670.38 7. Deductions -6,841.83 -6,841.83 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 1,213,828.55 -45,180.93 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate -45,180.93