Dept. of Trans. PROGRESS Serial No. Contract No. 16-264-09-41 05-1G2804 PROGRESS PAYMENT VOUCHER %complete: %time: 54% 72% Location: Federal Project: 05-VAR HSST-P 000C-414(E) Progress payment No. 004 Payment period ending: 09-20-16 PTM GENERAL ENGINEERING SERVICES INC 5942 ACORN ST RIVERSIDE CA 92504 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 578,520.00 52,580.00 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 64,488.96 -13,386.60 4. Earned Subject to Retention 643,008.96 39,193.40 5. Mobilization 30,000.00 0.00 6. Total Work Completed 608,520.00 7. Deductions -108,689.60 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 564,319.36 39,193.40 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 39,193.40