Dept. of Trans. PROGRESS Serial No. Contract No. 20-239-21-06 05-1G3004 PROGRESS PAYMENT VOUCHER %complete: %time: 80% 100% Location: Federal Project: 05-SB-0-0.0 SSTG-000C(505) 05-SLO-0-0.0 Progress payment No. 006 Payment period ending: 08-20-20 BC RENTALS INC DBA BC TRAFFIC SPECIALIST 638 W. SOUTHERN AVE ORANGE CA 92865 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 626,339.51 138,295.00 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 626,339.51 138,295.00 5. Mobilization 178,000.00 0.00 6. Total Work Completed 804,339.51 7. Deductions -272,359.90 -111,500.00 8. a. Contract Retentions b. Unsatisfactory Retentions 0.00 28,057.47 c. Reduction after 95% Comp. 9. Total pay to Contractor 531,979.61 54,852.47 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 54,852.47