Dept. of Trans. PROGRESS Serial No. Contract No. 21-204-18-20 05-1G3704 PROGRESS PAYMENT VOUCHER %complete: %time: 48% 24% Location: Federal Project: 05-SLO-46-49.6/49.6 NONE Progress payment No. 006 Payment period ending: 07-20-21 TSI ENGINEERING INC 4600 ROSEVILLE RD #140 NORTH HIGHLANDS CA 95660 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 577,631.35 52,570.23 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 98,187.00 0.00 4. Earned Subject to Retention 675,818.35 52,570.23 5. Mobilization 6. Total Work Completed 577,631.35 7. Deductions -4,000.00 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 671,818.35 52,570.23 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 52,570.23