Dept. of Trans. PROGRESS Serial No. Contract No. 21-326-13-34 05-1G3704 PROGRESS PAYMENT VOUCHER %complete: %time: 91% 80% Location: Federal Project: 05-SLO-46-49.6/49.6 NONE Progress payment No. 010 Payment period ending: 11-20-21 TSI ENGINEERING INC 4600 ROSEVILLE RD #140 NORTH HIGHLANDS CA 95660 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 1,077,482.18 254,697.00 2. a. Extra Work 25,259.61 0.00 b. Adustment Comp. 3. Materials on Hand 0.00 -98,187.00 4. Earned Subject to Retention 1,102,741.79 156,510.00 5. Mobilization 6. Total Work Completed 1,102,741.79 7. Deductions -2,000.00 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 1,100,741.79 156,510.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 156,510.00