Dept. of Trans. PROGRESS Serial No. Contract No. 23-142-16-48 05-1G4104 PROGRESS PAYMENT VOUCHER %complete: %time: 87% 86% Location: Federal Project: 05-SB-101-4.0/4.8 NONE Progress payment No. 009 Payment period ending: 05-20-23 GRANITE CONSTRUCTION COMPANY 5335 DEBBIE LN SANTA BARBARA CA 93111 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 8,782,929.50 723,984.24 2. a. Extra Work 222,784.76 14,243.68 b. Adustment Comp. 99,750.30 0.00 3. Materials on Hand 4. Earned Subject to Retention 9,105,464.56 738,227.92 5. Mobilization 1,130,000.00 0.00 6. Total Work Completed 10,235,464.56 7. Deductions -32,192.15 -27,301.15 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 10,203,272.41 710,926.77 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 710,926.77