Dept. of Trans. PROGRESS Serial No. Contract No. 17-111-15-20 05-1G4604 PROGRESS PAYMENT VOUCHER %complete: %time: 74% 75% Location: Federal Project: 05-SLO-101-R24.3/R24.3 NHP-P099(294) Progress payment No. 008 Payment period ending: 04-20-17 SOUZA CONSTRUCTION INC PO BOX 3810 SAN LUIS OBISPO CA 934033810 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 793,099.42 69,367.32 2. a. Extra Work 3,878.72 0.00 b. Adustment Comp. -1,978.50 0.00 3. Materials on Hand 4. Earned Subject to Retention 794,999.64 69,367.32 5. Mobilization 45,900.00 0.00 6. Total Work Completed 840,899.64 7. Deductions -71,608.31 -17,341.83 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 769,291.33 52,025.49 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 52,025.49