Dept. of Trans. PROGRESS Serial No. Contract No. 17-201-15-53 05-1G4604 PROGRESS PAYMENT VOUCHER %complete: %time: 89% 100% Location: Federal Project: 05-SLO-101-R24.3/R24.3 NHP-P099(294) Progress payment No. 011 Payment period ending: 07-20-17 SOUZA CONSTRUCTION INC PO BOX 3810 SAN LUIS OBISPO CA 934033810 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 1,018,412.79 39,768.22 2. a. Extra Work 6,716.44 0.00 b. Adustment Comp. -1,978.50 0.00 3. Materials on Hand 4. Earned Subject to Retention 1,023,150.73 39,768.22 5. Mobilization 45,900.00 0.00 6. Total Work Completed 1,069,050.73 7. Deductions -105,757.77 76,680.14 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 963,292.96 116,448.36 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 116,448.36