Dept. of Trans. PROGRESS Serial No. Contract No. 16-299-13-31 05-1G6304 PROGRESS PAYMENT VOUCHER %complete: %time: 81% 87% Location: Federal Project: 05-SLO-166-21.0/25.5 NONE 05-SB-166-21.0/25.5 Progress payment No. 005 Payment period ending: 10-20-16 CALPORTLAND CONSTRUCTION PO BOX 1280 SANTA MARIA CA 93456 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 2,043,873.04 246,130.26 2. a. Extra Work 59,261.59 24,544.28 b. Adustment Comp. 46,967.40 46,967.40 3. Materials on Hand 4. Earned Subject to Retention 2,150,102.03 317,641.94 5. Mobilization 279,000.00 0.00 6. Total Work Completed 2,429,102.03 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 2,429,102.03 317,641.94 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 317,641.94