Dept. of Trans. PROGRESS Serial No. Contract No. 18-201-10-58 05-1G9104 PROGRESS PAYMENT VOUCHER %complete: %time: 1% 41% Location: Federal Project: 05-MON-101 SSTG-000C(471) 05-SCR-101-0.0 05-SBT-101-0.0 Progress payment No. 001 Payment period ending: 07-20-18 HIGHWAY SPECIALTY COMPANY INC PO BOX 141 PALO CEDRO CA 96073 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 49,744.86 49,744.86 4. Earned Subject to Retention 49,744.86 49,744.86 5. Mobilization 3,750.00 3,750.00 6. Total Work Completed 3,750.00 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 53,494.86 53,494.86 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 53,494.86