Dept. of Trans. PROGRESS Serial No. Contract No. 19-084-08-07 05-1G9104 PROGRESS PAYMENT VOUCHER %complete: %time: 39% 49% Location: Federal Project: 05-MON-101 SSTG-000C(471) 05-SCR-101-0.0 05-SBT-101-0.0 Progress payment No. 006 Payment period ending: 03-20-19 HIGHWAY SPECIALTY COMPANY INC PO BOX 141 PALO CEDRO CA 96073 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 309,523.99 155,883.61 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 143,470.23 -35,255.65 4. Earned Subject to Retention 452,994.22 120,627.96 5. Mobilization 7,500.00 375.00 6. Total Work Completed 317,023.99 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 460,494.22 121,002.96 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 121,002.96