Dept. of Trans. PROGRESS Serial No. Contract No. 25-323-19-36 05-1G9504 PROGRESS PAYMENT VOUCHER %complete: %time: 9% 9% Location: Federal Project: 05-SCR-9-9.0/25.5 PTST-S009(29) Progress payment No. 007 Payment period ending: 11-20-25 GORDON N BALL INC 1777 OAKLAND BLVD #300 WALNUT CREEK CA 94596 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 427,005.00 242,710.00 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 196,545.20 5,442.83 4. Earned Subject to Retention 623,550.20 248,152.83 5. Mobilization 500,000.00 500,000.00 6. Total Work Completed 927,005.00 7. Deductions -5,000.00 -5,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 1,118,550.20 743,152.83 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 743,152.83