Dept. of Trans. PROGRESS Serial No. Contract No. 26-167-13-29 05-1G9504 PROGRESS PAYMENT VOUCHER %complete: %time: 35% 22% Location: Federal Project: 05-SCR-9-9.0/25.5 PTST-S009(29) Progress payment No. 016 Payment period ending: 06-20-26 GORDON N BALL INC 1777 OAKLAND BLVD #300 WALNUT CREEK CA 94596 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 2,571,889.75 657,840.50 2. a. Extra Work 230,506.96 -5,217.21 b. Adustment Comp. 3. Materials on Hand 128,221.49 -2,299.12 4. Earned Subject to Retention 2,930,618.20 650,324.17 5. Mobilization 950,000.00 0.00 6. Total Work Completed 3,752,396.71 7. Deductions -90,190.58 12,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 3,790,427.62 662,324.17 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 662,324.17