Dept. of Trans. PROGRESS Serial No. Contract No. 21-355-16-00 05-1H0204 PROGRESS PAYMENT VOUCHER %complete: %time: 1% 2% Location: Federal Project: 05-MON-101-R3.1/R5.2 ACNH-Q101(378) Progress payment No. 001 Payment period ending: 12-20-21 NEWTON CONSTRUCTION & MGMT INC PO BOX 3260 SAN LUIS OBISPO CA 93403 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 55,373.00 55,373.00 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 464,910.36 464,910.36 4. Earned Subject to Retention 520,283.36 520,283.36 5. Mobilization 6. Total Work Completed 55,373.00 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 520,283.36 520,283.36 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 520,283.36