Dept. of Trans. PROGRESS Serial No. Contract No. 23-058-13-20 05-1H0504 PROGRESS PAYMENT VOUCHER %complete: %time: 16% 4% Location: Federal Project: 05-MON-101-87.4/87.8 HSNH-Q101(405) Progress payment No. 004 Payment period ending: 02-20-23 GRANITE CONSTRUCTION COMPANY PO BOX 742478 LOS ANGELES CA 90074-2478 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 415,437.49 9,677.74 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 82,124.00 82,124.00 4. Earned Subject to Retention 497,561.49 91,801.74 5. Mobilization 375,000.00 125,000.00 6. Total Work Completed 790,437.49 7. Deductions -34,400.44 -12,950.44 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 838,161.05 203,851.30 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 203,851.30