Dept. of Trans. PROGRESS Serial No. Contract No. 23-361-21-55 05-1H0504 PROGRESS PAYMENT VOUCHER %complete: %time: 95% 39% Location: Federal Project: 05-MON-101-87.4/87.8 HSNH-Q101(405) Progress payment No. 011 Payment period ending: 12-20-23 GRANITE CONSTRUCTION COMPANY PO BOX 742478 LOS ANGELES CA 90074-2478 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 4,397,775.13 312,873.32 2. a. Extra Work 22,335.10 1,698.20 b. Adustment Comp. -6,911.12 -6,911.12 3. Materials on Hand 4. Earned Subject to Retention 4,413,199.11 307,660.40 5. Mobilization 500,000.00 0.00 6. Total Work Completed 4,913,199.11 7. Deductions -30,000.00 18,519.96 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 4,883,199.11 326,180.36 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 326,180.36