Dept. of Trans. PROGRESS Serial No. Contract No. 24-057-21-16 05-1H0504 PROGRESS PAYMENT VOUCHER %complete: %time: 97% 50% Location: Federal Project: 05-MON-101-87.4/87.8 HSNH-Q101(405) Progress payment No. 013 Payment period ending: 02-20-24 GRANITE CONSTRUCTION COMPANY PO BOX 742478 LOS ANGELES CA 90074-2478 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 4,432,190.04 6,012.91 2. a. Extra Work 115,857.89 11,475.36 b. Adustment Comp. -6,911.12 0.00 3. Materials on Hand 4. Earned Subject to Retention 4,541,136.81 17,488.27 5. Mobilization 500,000.00 0.00 6. Total Work Completed 5,041,136.81 7. Deductions -30,000.00 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 5,011,136.81 17,488.27 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 17,488.27