Dept. of Trans. PROGRESS Serial No. Contract No. 24-169-13-11 05-1H0504 PROGRESS PAYMENT VOUCHER %complete: %time: 99% 53% Location: Federal Project: 05-MON-101-87.4/87.8 HSNH-Q101(405) Progress payment No. 016 Payment period ending: 06-20-24 GRANITE CONSTRUCTION COMPANY PO BOX 742478 LOS ANGELES CA 90074-2478 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 4,463,486.52 12,538.50 2. a. Extra Work 190,965.03 13,814.18 b. Adustment Comp. -2,915.20 3,995.92 3. Materials on Hand 4. Earned Subject to Retention 4,651,536.35 30,348.60 5. Mobilization 500,000.00 0.00 6. Total Work Completed 5,151,536.35 7. Deductions -31,000.00 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 5,120,536.35 30,348.60 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 30,348.60