Dept. of Trans. PROGRESS Serial No. Contract No. 24-207-07-40 05-1H0504 PROGRESS PAYMENT VOUCHER %complete: %time: 99% 58% Location: Federal Project: 05-MON-101-87.4/87.8 HSNH-Q101(405) Progress payment No. 017 Payment period ending: 07-20-24 GRANITE CONSTRUCTION COMPANY PO BOX 742478 LOS ANGELES CA 90074-2478 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 4,467,086.52 3,600.00 2. a. Extra Work 190,965.03 0.00 b. Adustment Comp. -2,915.20 0.00 3. Materials on Hand 4. Earned Subject to Retention 4,655,136.35 3,600.00 5. Mobilization 500,000.00 0.00 6. Total Work Completed 5,155,136.35 7. Deductions -11,000.00 20,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 5,144,136.35 23,600.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 23,600.00