Dept. of Trans. FINAL Serial No. Contract No. 18-323-16-17 05-1H0704 PROGRESS PAYMENT VOUCHER %complete: %time: 100% 100% Location: Federal Project: 05-SBT-129-0.0/R2.6 NONE 05-SCR-9-13.1 05-MON-68-15.8/R17.1 Progress payment No. 011 Payment period ending: 04-03-18 SPECTRUM CONSTRUCTION GROUP INC 32 EDELMAN IRVINE CA 92618 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 874,080.85 0.00 2. a. Extra Work 16,918.06 9,485.05 b. Adustment Comp. 23,528.56 0.00 3. Materials on Hand 4. Earned Subject to Retention 914,527.47 9,485.05 5. Mobilization 82,225.00 0.00 6. Total Work Completed 996,752.47 7. Deductions 0.00 20,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 996,752.47 29,485.05 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 29,485.05