Dept. of Trans. PROGRESS Serial No. Contract No. 24-234-11-41 05-1H2304 PROGRESS PAYMENT VOUCHER %complete: %time: 60% 56% Location: Federal Project: 05-MON-218-R0.2/L0.9 NONE Progress payment No. 006 Payment period ending: 08-20-24 FBD VANGUARD CONSTRUCTION INC 550 GREENVILLE RD LIVERMORE CA 94550 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 753,982.81 29,684.27 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 753,982.81 29,684.27 5. Mobilization 120,000.00 0.00 6. Total Work Completed 873,982.81 7. Deductions -16,873.83 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 857,108.98 29,684.27 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 29,684.27