Dept. of Trans. PROGRESS Serial No. Contract No. 19-234-08-56 05-1H2904 PROGRESS PAYMENT VOUCHER %complete: %time: 18% 27% Location: Federal Project: 05-SB-101-13.8/R14.8 NONE Progress payment No. 002 Payment period ending: 08-20-19 CAL ELECTRO INC 3710 ELECTRO WAY REDDING CA 96002 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 153,681.00 152,393.50 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 204,459.00 204,459.00 4. Earned Subject to Retention 358,140.00 356,852.50 5. Mobilization 38,000.00 38,000.00 6. Total Work Completed 191,681.00 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 396,140.00 394,852.50 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 394,852.50