Dept. of Trans. PROGRESS Serial No. Contract No. 24-292-12-16 05-1H3104 PROGRESS PAYMENT VOUCHER %complete: %time: 34% 24% Location: Federal Project: 05-SB-154-R5.7/R6.2 ACST-S154(3) Progress payment No. 003 Payment period ending: 10-20-24 GRANITE CONSTRUCTION COMPANY PO BOX 742478 LOS ANGELES CA 90074-2478 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 2,008,720.44 699,993.20 2. a. Extra Work b. Adustment Comp. -10,526.10 -10,526.10 3. Materials on Hand 64,714.65 64,714.65 4. Earned Subject to Retention 2,062,908.99 754,181.75 5. Mobilization 764,067.90 160,856.40 6. Total Work Completed 2,762,262.24 7. Deductions -10,000.00 -10,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 2,816,976.89 905,038.15 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 905,038.15