Dept. of Trans. PROGRESS Serial No. Contract No. 24-355-10-30 05-1H3104 PROGRESS PAYMENT VOUCHER %complete: %time: 46% 43% Location: Federal Project: 05-SB-154-R5.7/R6.2 ACST-S154(3) Progress payment No. 005 Payment period ending: 12-20-24 GRANITE CONSTRUCTION COMPANY PO BOX 742478 LOS ANGELES CA 90074-2478 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 3,021,982.69 473,285.05 2. a. Extra Work 9,105.97 8,671.79 b. Adustment Comp. -10,526.10 0.00 3. Materials on Hand 64,714.65 64,714.65 4. Earned Subject to Retention 3,085,277.21 546,671.49 5. Mobilization 764,067.90 0.00 6. Total Work Completed 3,784,630.46 7. Deductions -66,000.00 -16,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 3,783,345.11 530,671.49 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 530,671.49